Many hurdles remain for Progress Energy's proposed nuclear power plant
Even if Progress Energy moves forward with plans to build a nuclear
power plant on a 3,000-acre tract in Levy County, there are plenty
of regulatory hoops that the utility company would have to jump
through before construction could begin.
Years of paperwork, public hearings and environmental and safety
tests are in the offing.
And even if everything goes smoothly, the plant would likely
not be ready to open before 2016.
Progress officials said Tuesday the company intended to file
for a combined construction/operating license permit with the
Nuclear Regulatory Commission.
But one of the first steps company officials must take is to
prove to the Florida Public Service Commission - the state's regulatory
authority for utilities - that a power plant is needed. Progress
officials have already indicated their primary evidence is a customer
base in its 35-county service area that they expect to grow by
25 percent in the next 10 years.
"You sit down (with the PSC) and say 'Here are our needs
and here's the technology we've decided on,'" said Buddy
Eller, Progress' Florida communications manager. Progress has
not yet decided on a vendor for the reactor.
A public hearing would be held within 90 days from the time Progress
filed its application of need, and then PSC commissioners would
make a decision on the application within a 135-day time frame,
said PSC spokesman Todd Brown. If the PSC approved the project,
then the matter would go to the state Department of Environmental
Protection for siting and approval.
The most significant hurdle for Progress to pass would be the
license review of the Nuclear Regulatory Commission. Roger Hannah,
spokesman for the NRC's regional office in Atlanta, said the process
is a lengthy one.
"It's about a three- to three-and-a-half-year process, more
or less," Hannah said.
The NRC's lengthy review would include:
-Studying physical characteristics of the plant site including
seismic, meteorological and geological data;
-The design of the reactor;
-The applicant's technical qualifications to operate the plant;
-Environmental impact including a study of possible discharges
from the plant;
-How staff at the power plant plan to respond to possible accidents.
A few months into the license review process, there would also
be a hearing required by federal law. If Progress does file for
a license then that meeting would be held in Levy County where
the public would be allowed to address questions or voice concerns
about the plant.
"It would be as close to the (plant) site as we can get
it so we can make it as accessible to as many people as possible,"
Hannah said.
While there are other opportunities for public hearings before
or during the construction process, those are possible only if
a person or group has demonstrated that the plant presents a danger
to the community or that NRC staff has not properly addressed
an environmental issue, Hannah said. If those hearings are required,
they would be held in front of a three-judge panel from the Atomic
Safety and Licensing Board.
Hannah said that if Progress does decide to build the plant and
the license is approved, then NRC inspectors would monitor every
step of the construction process. Once the plant is finished,
then the NRC would employ" resident" inspectors who
would live at or near the plant site to constantly monitor a plant's
performance.
"They are either at the site or available to get to the
site very quickly all the time," Hannah said.
In its timeline, Progress said if it does move forward with the
plant and its combined license is granted, then construction would
begin in 2010 or 2011.
Eller said if Progress does to decide to build then company officials
would welcome the opportunity to address public concerns during
the review process.
"Our intent is to be open and transparent and to try to
be as informative as possible," Eller said.